Parking the Avant seeding rail with 2 distributor heads separately

WARNING
Risk of injury due to implement tipping over.
Park the implement on stable and even ground.
WARNING
Risk of injury or even death due to tipping over of the seeding combination

Since the parking supports are not designed for the coupled seeding combination,

do not park the seeding combination on the parking supports.

Depending on the machine equipment, the parking supports can vary between the RoTeC coulters 1 and TwinTeC coulters 2.

  1. To set the coulter pressure to 0:

    Adjusting the coulter pressure hydraulically.
  2. To set the placement depth on the TwinTeC coulter to 0:

    Adjusting the scraper on the TwinTeC coulter
  1. Lift and fold the soil tillage machine with the coupled Avant seeding rail.
  2. Slide the inner parking supports 1 in the holder 3 on both sides.
  3. Secure the parking supports with pins 2.
  1. Unfold the soil tillage machine with the coupled Avant seeding rail.
  2. Install the outer parking supports 1 on the Avant seeding rail 2 on both sides.
  1. Remove the conveyor hoses 1 from the holder 2.
  1. If the Avant seeding rail has a tramline marker:

    Uncouple the yellow 2 tractor control unit of the Avant seeding rail from the soil tillage machine 1.
  2. Uncouple the red T pressureless return flow of the Avant seeding rail 2 from the soil tillage machine.
  1. Disconnect the green tractor control unit of the soil tillage machine 2 from the Comfort hydraulic system of the Avant seeding rail 1.
  1. Disconnect the supply line 3 for the rotary cultivator monitoring.
  2. Disconnect the lighting cable of the Avant seeding rail 1 from the soil tillage machine.
  3. Open the holder 5 for the supply lines.
  4. Remove the supply line to the interface of the hose package 6 .
  5. Open the holder 2 for the supply lines.
  6. Remove the supply line 4 of the job computer 3 from the centre frame.
  7. Park all of the electrical and hydraulic supply lines on the Avant seeding rail.
  1. Remove the nuts 3.
  2. Remove the bolts 1.
  3. Repeat the procedure on all of the brackets 2.
  1. Remove the distributor head holder from the roller frame.
  1. Remove the nuts 3.
  2. Remove the washers 2.
  3. Remove the stirrup bolt 1.
  4. Disconnect the connection on all distributor head holders.
  1. To park the machine:

    Slowly lower the soil tillage machine.

The soil tillage machine 3 is released from the hooks 4 of the Avant seeding rail.

The bracket 1 is no longer resting on the roller frame 2 of the soil tillage machine.

The Avant seeding rail is standing on the parking supports.

  1. Slowly drive the tractor with the coupled soil tillage machine 1 forward.