Removing the seeding shaft halves on implements with electric drive

NOTE
The lay shaft is only equipped on implements with tramline control.
  1. Use the lever 1 to set the bottom flap to scale value 8.
  1. Put the universal operating tool 3 on the locking mechanism 2.
  1. To open the locking mechanism,

    move the universal operating tool 2 up.

The metering unit cover 1 can be opened.

  1. Open the lay shaft bearings 1.
  1. Fold down the lay shaft 1.
  1. Loosen the bolt 2 on the gear wheels on the seeding shaft 1.
  1. Loosen the bolts 1 on the seeding shaft coupling.
  1. Loosen the bolts 1 of the adjusting rings on both halves of the seeding shaft.
NOTE
When pulling out the seeding shaft halves, make sure that the adjusting rings or coupling parts do not fall into the implement.
  1. Pull out the right half of the seeding shaft 1.
  1. To open the cover 1:

    Put the universal operating tool 3 on the adjustment spindle 2 and turn it clockwise.
  2. Fold up the cover.
  1. Take off the tension spring 1.
  2. Fold down the chain sprocket 3.
  3. Remove the drive chain 2.
  1. Remove the bolt 1.
  1. Remove the bolt 2 and nut 1.
  1. Take the gear wheel 1 off of the seeding shaft 2.
NOTE
When pulling out the seeding shaft halves, make sure that the adjusting rings or coupling parts do not fall into the implement.
  1. Pull out the seeding shaft 1.