Using the implement

  1. Align the implement parallel to the ground.
  2. Lower the implement on the field.
  3. Move the hydraulic system of the three-point power lift into float position.
  4. Switch on the tractor PTO shaft. Slowly couple the tractor PTO shaft only at an idle or at low tractor engine speed.
  5. To check the settings of the implement:

    Seed for 30m at working speed and then check the work pattern.
NOTE

Perform the following visual inspections regularly, e.g. after each reloading with seed:

  • Placement depth

  • Segment distributor heads

  • Coulters

  • Metering unit