Using the implement
REQUIREMENTS
The implement is unfolded
The parallelograms required for hoeing operation have been selected and moved into working position
The implement is set up and adjusted for operation
The implement is raised
If the headland is straight:
Drive into the field with the tractor until the parallelograms have reached the beginning of the plant rows
or
If the headland is slanted:
Drive into the field with the tractor until one of the two outermost parallelograms has reached the beginning of a plant row.
- Lower the implement on the field with the three-point power lift until the support wheels are resting on the ground.
NOTE
If the load on the support wheels is too high, the support wheels sink in.
- Use the three-point power lift to distribute the load on the tractor lower link and the support wheels.
- Drive off with the tractor.