Starting the spreading procedure

  1. Lift the machine to working height.
  2. To activate the oil circuit:

    Actuate the red tractor control unit.

or

Run the universal joint shaft at low tractor engine speed.

  1. Switch on the control terminal.
  2. In the Field menu, select Work.
NOTE

If the Work menu is exited while working, the system will automatically return to the Work menu after 10 seconds.

  1. Drive onto the field.
  1. If necessary, change the target rate in the Field menu.
  1. To run the spreading discs:

    Press . Then confirm with .

or

Run the universal joint shaft at low tractor engine speed.

Universal joint shaft speed

Spreading disc speed

3751/min

5001/min

4151/min

5501/min

4501/min

6001/min

5401/min

7201/min

6001/min

8001/min

6751/min

9001/min

7501/min

1.0001/min

  1. Press at the switch-on point

or

Open the left shutter or the right shutter

or

To switch the shutters automatically:

Switch on Section Control.
1

Shutter closed

2

Shutter open

  1. When the spreading procedure starts after longer road transport with a full spreader hopper:

    Ensure correct spreading.
  2. To start boundary spreading:

    Switch on the boundary spreading system. Drive around the field.
  3. Switch off the boundary spreading system after boundary spreading.