Calibrating the metering unit
Perform the calibration on all metering units consecutively. The sequence of the metering units can be freely selected.
- Unlock the locking lever 1 of the calibration conveyor section.
- Open the calibration flap 2.
If a double sluice is installed, activate the calibration conveyor section:
Unlock the control lever 3. Move it to the desired position.
- Take the calibration bucket 1 from the storage compartment.
- Push the calibration bucket into the holder 2 under the metering housing.
When 2 hoppers are combined, the corresponding metering units rotate simultaneously:
Prepare the other metering unit for calibration in the same way.
To start the calibration via the control terminal:
Refer to the ISOBUS software operating manual, Calibration menu.
- Perform the calibration with the desired calibration method.
- Hang the digital scale on the holder under the loading board.
To determine the weight of the spreading material:
hang the calibration bucket on the scale.
NOTE
To achieve a deviation of less than 3 percent:
Repeat the calibration test until the desired application rate is achieved.- Empty the calibration bucket.
NOTE
- Close the calibration flap 2.
- Lock the locking lever 1 on the metering housing.
- If equipped, perform the calibration in the same way on the second and third metering unit.
- Empty the calibration bucket and stow it in the storage compartment.