Emptying the fertilizer hopper via the metering unit
- Deactivate all fans.
If the implement has a double sluice:
Use the lever 2 to activate the conveyor section 1.
- Unlock the closing lever 1 on the metering unit housing.
- Open the calibration flap 2.
If only small residual quantities must be collected:
Slide the calibration container 1 into the receptacle 2
or
If larger residual quantities must be collected:
Place a suitable collection container under the metering unit housing.
To empty the hopper, the metering unit, and the metering roller:
See Emptying in the ISOBUS software operating manual.
To activate both conveyor sections:
Bring the lever 1 into the center position.
- Empty the calibration container.
For a new use:
Close the calibration flap 2. Lock the closing lever 1 on the metering unit housing.
or
For a longer period of decommissioning:
Leave the calibration flap open.
Accumulating condensation can flow out downward.
- If present, empty the other hopper chambers in the same way.