Adjusting the hydraulic supply
PREREQUISITES
Machine is lifted out
Protect the tractor from unauthorized operation
Firm and level hall floor
Instruct uninvolved persons to exit the danger zone
To seal the coulter pressure system after removal of the coulters:
Mount the connector 2 in the coulter pressure supply 1.
After conversion from small to large row widths, replace the short hydraulic hoses on the outer rows with long hydraulic hoses.
- Disconnect the connection 1 on row 1.
- Disconnect the connection 2 on row 2.
- Dismount the short hydraulic hoses 3.
- Mount the long hydraulic hoses between the coulters.
- Repeat the procedure for installing the hydraulic hoses on the opposite side of the machine.
After removing the coulters, the hydraulic coulter pressure system must be vented.
Instruct people to exit the danger area.
To set the coulter pressure to zero:
See the ISOBUS operating manual Adjusting the coulter pressure.- Switch on the fan with 2.0001/min.
NOTE
Ensure the oil supply in the hydraulic unit.
- Lift out and lower the machine 5x.
- Deactivate the fan.
Secure tractor and machine.
- Close the valve 3.
Mount the securing element 1.
Mount the bolt 2.
- Repeat steps 13 to 15 on the opposite side of the machine.