Starting spreading

REQUIREMENTS

  1. In the Main menu, select Working.
  2. Check the set working width and the set spreading area.
  3. If the working width and the spreading area are not as required:

    , Adjust the working width and , adjust the spreading area, Adjusting the working width and spreading area.
  4. Start the spreading disc drive.
  5. Confirm starting of the spreading disc drive.
  6. Start the spreading material metering unit.
  7. If pre-wetted salt should be spread:

    Switch on the brine addition.
  8. Start driving.

Spreading starts.

If a speed from the ISOBUS is selected under Source in the Speed menu, Configuring the source for the speed signal, the metering unit will regulate the spread rate depending on the actual driven speed starting at 0 km/h.

If the Simulated special equipment is selected under Source in the Speed menu, Configuring the source for the speed signal, the metering unit will regulate the spread rate depending on the speed that was entered under Simulated speed.

If the start-up ramp was activated and configured in the Start-up ramp menu, Configuring the start-up ramp, the metering unit will regulate depending on the values that were entered under Intended forward speed, Ramp start speed and Duration of the start-up ramp. The metering unit is activated above the ramp start speed and is regulated depending on the entered intended speed until the entered duration is reached.

  1. , Increase or reduce the target application rate, Changing the target spread rate.
  2. Double the spreading material quantity.
  3. , Change the working width and, spreading area.
  4. Stop.